Ballymore National Rugby Training Centre construction update - October 2022

Wed, Dec 7, 2022, 5:30 AM
Queensland Rugby Media Unit
by Queensland Rugby Media Unit

It's been another busy month at Ballymore with the National Rugby Training Centre (NRTC) taking shape. See below a list of items completed during the month of October:

  • Completed the remaining roof sheeting and box gutter install to the upper roof
  • Commenced the installation of the façade framing & back panning to all elevations
  • Completed the majority of services rough-in on ground floor with Level 1 now commencing
  • Commenced installation of the upper roof plant deck
  • Commenced framing to the eastern soffit overhanging the grandstand
  • Commenced formwork to the main entry reception stairs
  • Delivery of the mechanical AHUs and performance gym ceiling fans
  • Completed majority of internal framing to the ground floor with sheeting works commencing
  • Commenced structure works for the swimming pools
  • Commenced installation of the ground level and level 1 external window framing on all elevations
  • Commenced formwork installation to the main feature stairs located in the reception

Share
Wallace Charlie is excited for further tastes of the SVNS World Series. Photo: World Rugby
Wallace Charlie: The Erub entertainer ready to take on the world stage
Maddison Levi eyes LA gold, World Cup as superstar ready to channel learnings into World Series SVNS
Wallabies Test schedule locked in for 2026
Wallabies confirm Test schedule for 2026 season